WSJF (Weighted Shortest Job First) prioritizes by:

Answer options

A
Cost only
B
Value/Cost (cost of delay over job size)
C
Random order
D
Age of items

Correct answer: Value/Cost (cost of delay over job size)

Explanation

Quick AnswerThe correct answer is Value/Cost (cost of delay over job size) because it directly addresses the core logic of Agile & DevOps.

WSJF orders work by highest cost of delay divided by job size.