What is the purpose of a Sprint Retrospective in Scrum?
Answer options
A
To demonstrate completed work to stakeholders
B
To plan the next sprint's backlog items
C
To inspect the team's process and identify improvements for the next sprint
D
To estimate story points for upcoming user stories
Correct answer: To inspect the team's process and identify improvements for the next sprint
Explanation
Quick AnswerThe correct answer is To inspect the team's process and identify improvements for the next sprint because it directly addresses the core logic of Agile & DevOps.