Scrum, increment must be…

Answer options

A
Potentially shippable/usable at sprint end
B
Only a document
C
A mock-up only
D
Untested code

Correct answer: Potentially shippable/usable at sprint end

Explanation

Quick AnswerThe correct answer is Potentially shippable/usable at sprint end because it directly addresses the core logic of Software Engineering.

Definition of Done ensures quality and usability.