Planning Poker is used for:

Answer options

A
Release planning only
B
Relative estimation by team
C
Risk management only
D
Daily Scrum

Correct answer: Relative estimation by team

Explanation

Quick AnswerThe correct answer is Relative estimation by team because it directly addresses the core logic of Agile & DevOps.

Team members estimate using cards to reach consensus.