Agile & DevOps
Accenture Technical PrimermediumAgile & DevOpsGeneral

During Sprint Planning, the team commits to:

Answer options

A
Scope that never changes
B
A Sprint Goal and selected items
C
Fixed dates for release
D
All items requested by stakeholders

Correct answer: A Sprint Goal and selected items

Explanation

Quick AnswerThe correct answer is A Sprint Goal and selected items because it directly addresses the core logic of Agile & DevOps.

Sprint Planning creates a Sprint Goal and selects PBI to meet it.