During Sprint Planning, the team commits to:
Answer options
A
Scope that never changes
B
A Sprint Goal and selected items
C
Fixed dates for release
D
All items requested by stakeholders
Correct answer: A Sprint Goal and selected items
Explanation
Quick AnswerThe correct answer is A Sprint Goal and selected items because it directly addresses the core logic of Agile & DevOps.
Sprint Planning creates a Sprint Goal and selects PBI to meet it.